CONSTRUCTION ACTIVITIES

Jetty

The construction of the hydraulic structure of the two petrochemical jetties on both Western & Eastern side of PMB, as well as the auxiliary housing works  have been completed and is now awaiting the approval of License to Operate.

Co-generation Power Plant

The co-generation power plant at Pulau Muara Besar will be the main power source provider for the whole refinery and petrochemical plant.

To date, the construction of the main Gas Insulated Switchgear (GIS) substation and other associated facilities has been completed. Some boilers have been put into use and electricity is currently bring produced by the co-generation power plant. The priority now is to resume installations of the boilers until fully completed and that the power plant is operating at its maximum capacity.

Seawater Desalination Facility

The construction of the seawater desalination facility has been completed by the end of January. Desalted water is currently being produced which will be used domestically as well as by the power plant.

Refinery & Petrochemical Complex

The focus for the Refinery & Petrochemical Complex is the concurrent installation of the steel structure works, the installation of equipment, and the installations of heating furnaces.

MAJOR OFF SITE BOUNDARY LIMIT & OTHER ACTIVITIES

Eastern Channel Dredging

Dredging of the Eastern Channel involves deepening of the Eastern Channel to allow up to 50,000 DWT vessels to PMB and a concurrent backfilling of dredged materials to elevate the areas under Hengyi’s Phase 2 land development plan.

Utilities

66kV transmission link project which entails cable laying from Muara substation through the PMB bridge connecting to Hengyi’s substation at PMB is in progress. This will provide power for construction, testing and commissioning and eventually serve as an emergency back-up power for the for the refinery plant.